Katihar Railway Division has announced a special mega block from June 5 to June 14, 2026, for doubling work on the Katihar-Sonauli-Kuaripur section. This technical project includes pre-non interlocking and commissioning of the new double line. Due to this, several trains will be cancelled or diverted to ensure the work is completed safely.
ℹ️: Rajdhani Express: Route diverted via Purnia on June 14, 13 trains affected।
Which trains are cancelled and diverted?
A total of 27 trains have been cancelled during this period. Some express trains will be partially cancelled or their routes changed to manage traffic. Purnia Junction Manager Munna Kumar stated that several passenger, DMU, and MEMU trains are affected on different dates.
| Train Number/Name | Impact | Dates |
|---|---|---|
| 55729/55730 Katihar-Radhikapur Passenger | Fully Cancelled | 11-14 June |
| 55702/55701 Katihar-Malda Town Passenger | Fully Cancelled | 10-14 June |
| 63308/63305 Samastipur-Katihar MEMU | Fully Cancelled | 10-14 June |
| 15719/15720 Katihar-Siliguri Jn Express | Fully Cancelled | 11-13 June |
| 15723/15724 Jogbani-Siliguri Town Express | Fully Cancelled | 11-14 June |
| 13159 Kolkata-Jogbani Express | Ends at Katihar | 10 & 12 June |
| 13160 Jogbani-Kolkata Express | Starts from Katihar | 11 & 13 June |
What is the schedule for technical work and inspection?
The technical activities, including non-interlocking work, will take place between June 6 and June 13, 2026. Following the completion of these tasks, the Commissioner of Railway Safety (CRS) is scheduled to inspect the section on June 14, 2026. Railway officials mentioned that this project will improve train speed and punctuality once finished.
How can passengers check their train status?
The railway administration has advised passengers to verify their train status before starting their journey. Information is available via the railway helpline 139, the National Train Enquiry System (NTES), the official railway website, or the mobile app. Additionally, the Bhagalpur-Katihar special train service has been extended until June 22, though it will only run between Bhagalpur and Naugachia from June 10 to June 16.
Frequently Asked Questions (FAQs)
कटिहार-सोनैली-कुआरीपुर रेलखंड पर मेगा ब्लॉक कब से कब तक है?
यह विशेष मेगा ब्लॉक 5 जून से 14 जून 2026 तक निर्धारित है, जिसमें तकनीकी कार्य और CRS निरीक्षण शामिल है।
क्या कोलकाता-जोगबनी एक्सप्रेस पूरी तरह रद्द है?
नहीं, ट्रेन 13159 कोलकाता-जोगबनी एक्सप्रेस 10 और 12 जून को कटिहार स्टेशन पर समाप्त होगी और 13160 जोगबनी-कोलकाता एक्सप्रेस 11 और 13 जून को कटिहार से शुरू होगी।