The long-standing dream of residents in Panna district is turning into reality as trains prepare to reach Devendranagar. The local community expressed great joy and celebrated with sweets as the project reached its final stages. This railway connectivity is a result of long struggles by the Rail Bring Struggle Committee and local representatives.
What is the current status of Devendranagar railway line
The railway project has seen significant progress with the construction of Devendranagar station starting in March 2020. A successful trial run was conducted on the ready track between Nagod and Phulwari (Devendranagar) on 25 March 2026. The 7 km track from Phulwari to Devendranagar was in its final phase by April 2026.
Key dates and milestones for train operations
| Event/Milestone | Date/Timeline |
|---|---|
| Station construction start | March 2020 |
| Nagod to Devendranagar (20km) target | December 2025 |
| Nagod-Phulwari Trial Run | 25 March 2026 |
| Phulwari-Devendranagar Trial window | 25-30 April 2026 |
| Expected full operation | May 2026 |
| Important Test Trial | 10 June 2026 |
Who are the key authorities involved in the project
The project is being executed by the West Central Railway (WCR) and Rail Vikas Nigam Limited (RVNL). SDO A.K. Pandey and EE S.K. Richharia have provided technical updates on the construction and testing. The Commissioner of Railway Safety (CRS) will handle the speed trials and safety inspections before the line opens for the public.
Frequently Asked Questions (FAQs)
देवेंद्रनगर में ट्रेन का ट्रायल कब होगा?
फुलवारी-देवेंद्रनगर सेक्शन के लिए 10 जून 2026 को एक महत्वपूर्ण परीक्षण ट्रायल होने की संभावना है।
स्टेशन का काम कब तक पूरा होगा?
रेलवे SDO ए.के. पाण्डेय के अनुसार स्टेशन का निर्माण कार्य तेजी से जारी है और मई 2026 तक पूरा होने की उम्मीद है।