The Dhamtari-Kendri rail line project is moving toward its final stages. Railway officials recently conducted fresh measurements to remove encroachments to make way for staff quarters and a rest house. This development is part of the larger effort to start broad gauge train services in Dhamtari by August 2026.
When will train services start in Dhamtari?
The target to start passenger services on the broad gauge line in Dhamtari is August 15, 2026. According to Mayor Ramu Rohra and Collector Avinash Mishra, a trial run could potentially begin within 15 to 20 days after their June 2026 inspection. The trial run is expected by the end of July, and the rack point work should be finished by the end of August.
What is the current status of construction and encroachment?
The railway department has been actively clearing illegal structures to ensure smooth project completion. Major demolition drives took place in April 2025 and April 2026, using bulldozers and JCBs to remove houses and shops near the station and bus stand. Currently, the station building is about 80% complete, and most of the track laying for the 70 km stretch from Raipur to Dhamtari is finished.
Project Timeline and Key Milestones
| Date/Timeline | Event/Milestone |
|---|---|
| September 7, 2021 | Project approval for 50 km line from Dhamtari to Kendri |
| September 18, 2025 | Rail operations started from Raipur to Kendri and Rajim |
| December 2025 | Target for broad gauge conversion from Abhanpur to Dhamtari |
| November 16, 2025 | Station building work reached 80% completion |
| August 15, 2026 | Target date for starting passenger services in Dhamtari |
Frequently Asked Questions (FAQs)
धमतरी में ट्रेन कब से चलेगी?
धमतरी में बड़ी रेल लाइन पर यात्री सेवाओं को शुरू करने का लक्ष्य 15 अगस्त, 2026 रखा गया है।
स्टेशन पर क्या सुविधाएं मिलेंगी?
धमतरी स्टेशन को आधुनिक बनाया जा रहा है, जिसमें आरक्षण काउंटर, वेटिंग हॉल और दिव्यांगजनों के लिए विशेष सुविधाएं शामिल होंगी।